Markets rocked as US says Israel has struck Iran    Israel carries out strike inside Iran, US says as region braces for further escalation Explosions heard near military base    7,700 commercial disputes resolved via Taradhi platform, says Ministry of Justice    Dhul Qadah 29 is the last day for Umrah pilgrims to leave the Kingdom 90-day duration of visa begins from the date of entering the Kingdom; Hajj Ministry clarifies    'Saudi hospitality sector to generate SR42 billion investments and 120,000 jobs by 2030'    Chinese workers disagree with West over mass production claims    IMF forecast: Saudi economy to record 2nd highest global growth rate in 2025    Centuries-old defensive moat and fortification wall unearthed in Historic Jeddah    EU's Josep Borrell warns Middle East 'on edge of regional war'    Indonesia issues tsunami alert after volcano erupts on remote island    US Senate kills the articles of impeachment against Alejandro Mayorkas    Poignant shot from Gaza wins World Press Photo of the Year 2024    Al Ain ends Al Hilal's record streak with a 4-2 win in AFC Champions League semi-final    Saudi Pro League postpones Al-Hilal vs. Al-Ahli match; Al-Ahli rejects rescheduling    50% traffic fine reduction takes effect    'Zarqa Al Yamama': Tickets now available for Saudi Arabia's first opera premiering April 25    AFC postpones Al Ain vs Al Hilal semi-final match due to weather conditions    Turki Alalshikh announces groundbreaking 5 vs 5 Riyadh Season bout featuring international boxing stars    Diriyah Biennale Foundation announces shortlist for AlMusalla Prize, set to revolutionize musalla architecture    Fourth Gulf Film Festival kicks off in Riyadh, scaling up Saudi movie industry Event extends over 5 days with the screening of 29 diverse films    JK Rowling in 'arrest me' challenge over hate crime law    Trump's Bible endorsement raises concern in Christian religious circles    Hollywood icon Will Smith shares his profound admiration for Holy Qur'an    We have celebrated Founding Day for three years - but it has been with us for 300    Exotic Taif Roses Simulation Performed at Taif Rose Festival    Asian shares mixed Tuesday    Weather Forecast for Tuesday    Saudi Tourism Authority Participates in Arabian Travel Market Exhibition in Dubai    Minister of Industry Announces 50 Investment Opportunities Worth over SAR 96 Billion in Machinery, Equipment Sector    HRH Crown Prince Offers Condolences to Crown Prince of Kuwait on Death of Sheikh Fawaz Salman Abdullah Al-Ali Al-Malek Al-Sabah    HRH Crown Prince Congratulates Santiago Peña on Winning Presidential Election in Paraguay    SDAIA Launches 1st Phase of 'Elevate Program' to Train 1,000 Women on Data, AI    41 Saudi Citizens and 171 Others from Brotherly and Friendly Countries Arrive in Saudi Arabia from Sudan    Saudi Arabia Hosts 1st Meeting of Arab Authorities Controlling Medicines    General Directorate of Narcotics Control Foils Attempt to Smuggle over 5 Million Amphetamine Pills    NAVI Javelins Crowned as Champions of Women's Counter-Strike: Global Offensive (CS:GO) Competitions    Saudi Karate Team Wins Four Medals in World Youth League Championship    Third Edition of FIFA Forward Program Kicks off in Riyadh    Evacuated from Sudan, 187 Nationals from Several Countries Arrive in Jeddah    SPA Documents Thajjud Prayer at Prophet's Mosque in Madinah    SFDA Recommends to Test Blood Sugar at Home Two or Three Hours after Meals    SFDA Offers Various Recommendations for Safe Food Frying    SFDA Provides Five Tips for Using Home Blood Pressure Monitor    SFDA: Instant Soup Contains Large Amounts of Salt    Mawani: New shipping service to connect Jubail Commercial Port to 11 global ports    Custodian of the Two Holy Mosques Delivers Speech to Pilgrims, Citizens, Residents and Muslims around the World    Sheikh Al-Issa in Arafah's Sermon: Allaah Blessed You by Making It Easy for You to Carry out This Obligation. Thus, Ensure Following the Guidance of Your Prophet    Custodian of the Two Holy Mosques addresses citizens and all Muslims on the occasion of the Holy month of Ramadan    







Thank you for reporting!
This image will be automatically disabled when it gets reported by several people.



Why costlier 14 MW turbines actually reduce the large-scale farm bill
Published in The Saudi Gazette on 18 - 09 - 2020

Siemens Gamesa's massive 14-megawatt (MW) wind turbine is set to become commercially available from the mid-2020s, furthering the industry's push for larger and more efficient facilities. A Rystad Energy analysis shows that although they are more expensive to manufacture, choosing these giant turbines actually reduces overall costs for large-scale offshore wind farms.
Their added costs are expected to be mitigated by fewer required units and the efficiency gains associated with the newer, more technologically advanced turbines.
For every project, there is also the cost of manufacturing a number of foundations, so the reduction in the number of turbines will also lead to fewer array cabling runs, which in turn reduces the installation scope.
Rystad Energy analyzed the cost of using turbines of differing sizes for the case of a 1 gigawatt (GW) offshore project. The SG 14-222 DD model will leapfrog GE's new 12 MW Haliade-X prototype and become the largest turbine available, globally. At the moment, the largest turbines to be commissioned between 2020 and 2021 have nameplate capacities of up to 10 MW.
Utilizing 14 MW turbines instead of 10 MW ones, the number of units required for a 1 GW project falls by 28 units, from 100 to 72. Moving to a 14 MW turbine from a 12 MW turbine still offers a reduction of nearly 11 units. Overall, the analysis shows that using the largest turbines for a new 1 GW windfarm offers cost savings of nearly $100 million versus installing the currently available 10 MW turbines.
"Siemens Gamesa's newest turbine is a step towards dramatically reducing development and levelized costs world-wide. With larger turbines come greater savings in other project segments and greater revenue generation potential over the duration of future projects, increasing the offshore wind industry's competitiveness," said Rystad Energy's product manager for offshore wind, Alexander Flotre.
In this example, we assume that the cost of a turbine is approximately $800,000 per MW on average for currently available units (i.e. turbines with up to 10 MW nameplate capacities), with a 2.5% premium applied for each additional MW for the larger units expected in the medium-term, to reflect anticipated efforts by manufacturers to capture upside.
Thus, for this analysis we estimate that the cost of a 10 MW turbine is $8 million, while a 12 MW and a 14 MW turbine would cost approximately $10.1 million and $12.3 million, respectively. Therefore, moving from a 10 MW turbine to a 14 MW turbine could result in higher costs of approximately $85 million for manufacturing, while utilizing a 14 MW turbine in lieu of a 12 MW unit could add almost $45 million to manufacturing costs.
Foundations are the main components that offer opportunities for cost reductions if larger turbines are utilized. Rystad Energy estimates that a foundation typically costs between $3 million and $4 million, with variations relating largely to foundation type and water depth. In a 10 MW to 14 MW switch, such cost savings could surpass $100 million for the developer, while savings in a 12 MW to 14 MW scenario would likely range from $30 million to $50 million.
The cost of array cables varies based on the turbine size. While the use of larger turbines implies potential cost savings through fewer foundations, the added length required for array cables for 14 MW turbines is likely to keep overall cable costs flat. However, the lower turbine count reduces the number of cabling runs and connection of turbines to the offshore substation, which in turn could cut installation costs.
This example shows that while larger units are expected to drive up the cost of turbines, reductions from other segments — namely foundations — could result in cost savings of $100 million to $120 million on manufacturing alone, helping to offset some of the developer's expenses.
Rystad Energy also estimates that the cost to install a turbine ranges between $0.5 million to $1 million, while the cost of foundation installation ranges from $1 million to $1.5 million per unit. Using the midpoint in each range, for a 1 GW project the implied savings surpass $50 million if using 14 MW instead of 10 MW units.
Under similar circumstances but comparing 14 MW against 12 MW turbines, potential savings are beyond $20 million. Furthermore, the reduction in cabling runs and connections due to the lower number of array cables could lead to additional savings of between $5 million and $15 million when using 14 MW turbines rather than 12 MW and 10 MW turbines.
On top of potential cost savings from the reduction in units, the increase in turbine size can also drive other efficiency gains. Rystad Energy has analyzed the potential reduction in the levelized cost of energy (LCOE) using Equinor's Empire Wind in the US as a case study.
In this case, using 10 MW turbines, the estimated LCOE is approximately $75/MWh. Opting instead for 12 MW turbines, the LCOE falls to approximately $71/MWh. With a further upgrade to 14 MW turbines, the LCOE is estimated to be $68/MWh. Thus, with the incremental increases in size, turbines and offshore wind plants become more economical – not just in lower upfront costs, but also in longer-term power generation potential. — Rystad Energy